Structural steelwork, Welling, Kent #2

This is part 2 of this project, to see it from the beginning Click Here

Day 4, with the concrete poured yesterday, I have to first build up 800mm to floor level, for this I have used solid concrete blocks.

wss10

With a late delivery the brick pier and old doorway were finally finished by 8:00pm on day 4, not once did it enter my mind that it wouldn’t be done.

wss11

Day 5, extra request for another opening.

Final day, Finally done, now it’s all down to the plasterers